News and events

There's always something happening. We'll keep this page updated with major events and items of interest, but if you’d like to be contacted directly with information about upcoming events, please register here if you haven't already.

September 2016

Village Green Spring 2016

The days are getting warmer with the arrival of Spring! Soak up some sun and read about what has been happening at our Greengate Villages.

August 2016

Progress at St Patrick's Green

The crane is up and running and lifting a large amount of formwork & steel into the site in readiness for our fast moving concrete structure. We have already completed our lower car park slab on ground and are around 20% through our first suspended slab level. In the coming weeks we will start to see the O’Farrell building’s lift & stair core pop its head up above ground!

Brookfield Multiplex are moving fast while maintaining a great quality of construction at the same time. Exciting times head!

July 2016

Christmas in July 2016

Today we celebrated Christmas in July with our wonderful future residents at the St George Motor Boat Club.

Our guests enjoyed beautiful weather, great company and lots of laughs, as well as a delicious three course lunch and some classic Christmas themed musical hits.

Residents also heard from David, our lead architect who was able to explain how much thought and processes have gone into the design and development of St Patrick's Green. We think David should come along more often to our events!

A big thank you to everyone who attended this year's Christmas in July function - we look forward to seeing you all at our next event!

 

 

July 2016

A Momentous Day at St Patrick's Green

Today is a momentous day, as far as building goes!

Today we poured our first slab, which means we have started to build St Patrick's Green. Everything that has happened on site to date has been what's called "enabling works", but today we actually built our first bit of the structure, albeit a ground slab.

The next big moment will be our first suspended slab, a post tensioned slab. This is where we introduce some of the complex engineering structure to the project. Stay tuned for more updates on how construction is progressing.

July 2016

The Crane has arrived!

St Patricks Green has reached another milestone.

Last Saturday the crane was erected on site and Brookfield Multiplex have started the next construction phase.

June 2016

Village Green Winter 2016

The days are getting colder as we make our way into Winter. Read all about what has been going on at our Greengate Villages in this quarter's edition of the Village Green.

May 2016

Coffee Club May 2016

We had another successful Coffee Club on the 11th of May at the St George Leagues Club for purchasers of St Patrick's Green. Paul and Brendan, Project and Construction Managers from Brookfield Multiplex, came along and gave a presentation and updated residents on how construction is progressing.

Here are some photos from the day!

April 2016

Village Green Autumn 2016

With Autumn upon us, find out what has been happening across all of our Greengate Villages.

April 2016

Early works are nearly complete!

The early works at St Patrick's Green are nearly complete!

The excavation, footings, in ground storm water pipework are all being finished in readiness to commence building (lots of concrete) very soon!

December 2015

Village Green Summer 2015/16

With Summer in full swing, find out what's been happening across our Greengate Villages.